A six megawatt system…

was installed by GSL Electric for this project. The amount of underground, excavation, and conduit installed was impressive by any standard. And everything had to be precise—within inches. “Close enough” definitely would not cut it on a mission-critical project such as this one. GSL Electric also installed 15 separate diesel generators that could provide power to Switch clients in the case of a power outage, as part of this project's scope.

  • Completed | 2016

  • SQFT | 479,136

  • Client | Martin-Harris Construction